WisDOT work on I-94 to close lanes in numerous areas this week

CREATED Feb. 12, 2013

  • Print
  • PHOTO; KRISTYNA WENTZ-GRAFF / KWENTZ@JOURNALSENTINEL.COM Image by Kristyna Wentz-Graff

MILWAUKEE - The Wisconsin Department of Transportation will be repairing the roads on I-94 this week.

During the week, the following projects will close some lanes -

Feb. 11-14 -- I-94 Westbound/I-43 Northbound will close one left lane at Howard Ave. starting at 8:00 p.m., and two left lanes will close starting at 9:30 and ending at 5:30 a.m. each day.

Feb. 12-14 -- I-94 Eastbound will close the two left lanes at the Milwaukee/Racine County line each night starting at 7:00 p.m. and ending at 5:00 a.m. each morning.

Feb. 12-12 --I-94 Westbound will close the left two lanes at STH 158 starting at 7 p.m. and ending at 11:45 p.m. each night.

Feb. 13-14 --I-94 Westbound will close the left two lanes at the Kenosha/Racine County line startin each night at 7 p.m. and ending at 5 a.m.

Feb. 14-15 --I-94 Westbound/I-43 Northbound will close the right two lanes at Howard Ave. starting at 9:30 p.m. and ending at 5:30 a.m. each day.

Feb. 15-16 --I-94 Westbound/I-43 Northbound will close the right two lanes at Howard Ave. starting at 9:30 p.m. and ending at 5:30 a.m. each day.

During the year of 2013, WisDOT plans to complete the following projects on I-94.

Milwaukee County

Rawson Ave Interchange Project at I-94
Project includes reconstruction and widening of the Rawson Ave bridge over I-94 and the reconstruction of the I-94 exit/entrance ramps at Rawson Ave.

Ryan Rd Ramps Project at I-94
Project includes construction of new ramp structures for I-94 WEST (NB) exit to Ryan Rd, and the Ryan Rd entrance ramp to I-94 EAST (SB).

Racine County

County G to WIS 20 Frontage Roads Project
Project includes reconstruction/realignment of the frontage roads between County G and WIS 20. This project also includes the separation of the "scissor" ramps and frontage roads at County K.

Kenosha County

I-94 Mainline Project from WIS 50 to WIS 142
Project includes reconstruction/widening of I-94 WEST (NB) between WIS 50 and WIS 142. This project also includes reconstruction of the I-94 WEST (NB) exit/entrance ramps at WIS 50, WIS 158, and WIS 142. This project is a combination of 2 projects - the second year of a two-year mainline project between WIS 50 and WIS 158, and the first year of a two-year mainline project between WIS 158 and WIS 142.

WIS 50 Local Road Project
Project includes reconstruction and new construction of roadways in the NW and SW quadrants of the WIS 50 & I-94 interchange. This is a two-year project that includes work on WIS 50 at I-94 in 2014.